NSTX Program, 10/30/97
Proposed Process
We envision 5 sequential steps in this process, spanning September 1997 through September-October 1998:
- Scientific Priorities and Available Research (9-10/97)
- Research Forum and Working Group Reports (10-12/97)
- Research Proposals and Program Outline (1-3/98)
- DOE Review and Approval (4-9/98)
- Research Team and Tasks Plan for FY 1999 (9-11/98)
1) Define Scientific Priorities and Announce Available Research (9-10/97)
- NSTX PAC met during September 17-18, 1997.
- The PAC submits the meeting report in two weeks.
- Notice of Available Research on NSTX for FY 1999-2001 issued and can be viewed at http://fileroom.pppl.gov/nstxhome/index.html, under "NSTX Research Program."
2) Hold Research Forum and Produce Working Group Reports (10-12/97)
- FY-98 NSTX Research Forum announced and can be viewed at http://fileroom.pppl.gov/nstxhome/index.html, under "NSTX Research Program," "Meetings."
- NSTX Research Forum on December 3-5, 1997.
- Solicit during Research Forum Letters of Interest for participation in research on NSTX during FY 1999-2001.
- OFES of DOE issues in 12/97 request for proposal to carry out collaborative research on NSTX.
- The NSTX Working Groups issue in about 2 weeks following the Forum the Working Group reports.
3) Develop Integrated Proposals and Outline NSTX Research Program (1-3/98)
- Draft PPPL pre-proposals by January 20, 1998.
- Letters of Interest due on January 20, 1998.
- OFES of DOE issues in 1-2/98 initial budget guidance for FY 1999.
- Draft FY-99 NSTX Research Program Proposal formulated in 2/98.
- NSTX PAC meets in 2/98 to advise on Draft FY-99 Proposal.
- The PAC submits the meeting report in two weeks.
- The PPPL Director issues in 3/98 the NSTX Program Outline.
- Draft FY-99 NSTX Research Program Proposal updated and distributed in 3/98.
- DOE FWP meeting in 3/98.
4) DOE Review and Approve Proposals (4-8/98)
- The OFES of DOE reviews Field Work and Grant Proposals and make decisions on funding.
5) Form Research Team and Develop Tasks Plan for FY 1999 (8-10/98)
- NSTX Program Executive Committee formed in 8-9/98.
- NSTX Research Team Meeting held in 9-10/98.
- National NSTX Research Plan for FY 1999 issued in 10/98.
- The task teams and NSTX facility and research operation groups formulate and propose to the Executive Committee in 10-11/98 detailed plan for task execution.
- Working NSTX FY-1999 experimental run plan issued in 11/98.